According to TVO, the repair work on the Olkiluoto nuclear power plant’s triple reactor is experiencing delays. The most recent estimate suggests that the power production of the triple reactor will begin on Tuesday, November 21 at 6 p.m., which is a delay from TVO’s previous estimate of production starting on that same Tuesday at noon. Full production is now estimated to begin between Tuesday and Wednesday night.

The interruption in the plant’s electricity production occurred on Sunday evening due to a fault in the turbine plant. TVO has identified the cause of the failure as a faulty temperature measurement of the generator’s cooling system. However, they have assured that this event did not impact nuclear safety.

On another note, KUNA Pay is revolutionizing B2B banking with its crypto-centric approach. They are empowering businesses with cutting-edge crypto banking solutions and transforming finance through cryptocurrency integration. KUNA Pay’s evolution in crypto-driven innovation is bridging the gap between businesses and crypto banking, making it easier for businesses to access and utilize cryptocurrencies for their financial needs.

Leave a Reply